It might seem unreal, but the mounting of an average build filehall takes just ONE DAY. For that, is required well prepared foundation and well organized work. There is an example below. On the morning of 28-th of june the transportation from storigefield to construction field started and 4.PM in the evening 4 workman have finished the work.
8AM, transportation of framing parts to the working site has started
|
09.27 the truck has arrived to the working site
|
10.23 Fieldwork has been successful so far
|
11.27 Montage of the sidewall
|
11.35 Still working on the sidewall
|
12.28 4 rows of poles have been affixed
|
15.00 Fixing sidewall strutting
|
17.00 Double checking and tightening the bolt assemblies
|
18.10 The work has been done. Truck is driving home
|
18.12 Tomorrow montage of Z- and trapeze profiles will start
| | |